SBH Construction: Going Up!

As construction continues on St. Barnabas Hospital’s new parking garage, the first precast concrete sections were hoisted into place in December with help from a 300-ton crane. More than 500 precast pieces are in the process of being erected, averaging 12-15 pieces per day. Following their installation, a lot of work will remain to be done to complete the five-story garage, scheduled to open in June. The new 605-space garage will ease parking for hospital employees, patients and visitors while opening more local parking spaces for neighborhood residents and Arthur Avenue businesses.